New Linear Accelerator
Investment will ensure continued world-leading discovery, innovation
The Canadian Light Source (CLS) at the University of Saskatchewan is replacing its linear accelerator (linac), the device that speeds up electrons to produce a beam of light researchers use to study materials at a molecular or cellular level. This critical replacement will ensure the CLS continues to deliver high-quality, stable and reliable light to the over 1,000 scientists from across Canada and around the world who use the CLS each year for research related to health, agriculture, environment and advanced materials.
In May 2024, we began a project to replace our linac with a new unit that will improve the efficiency and reliability of the light beam. For the latest updates, check back on this page or follow us @canlightsource on social media for #newlinac posts.
Critical Milestones on the Path to Beam
The critical milestones on the path to beam, along with estimated remaining durations are listed below. These timelines represent best estimates based on current progress and planning. There remains significant uncertainty associated with many of these steps, specifically the highlighted items which are outside of our routine operations. Timelines are subject to change as commissioning activities advance and new information becomes available.
☑ | Component Qualification (Completed) – Isolating and testing each individual component of the system through RF conditioning. At completion of this step, four components did not pass and have been replaced with critical spares. | - |
☑ | Complete System Bakeout (Completed) – Using external heating elements to drive off residual gases and contaminants in the system. Following completion of this step, vacuum conditions within the LINAC are significantly improved. | - |
☐ | RF Conditioning (In progress) – The process of gradually introducing and increasing RF power to the system. This allows the internal surfaces to adapt to high electric fields, and over time, the system “conditions” itself to handle higher power levels without breakdowns or arcing. | 4 weeks |
☐ | LINAC Setup and Stable Beam - Configuring the LINAC to produce a consistent, stable electron beam suitable for injection into the booster ring. | 3 weeks |
☐ | Beam Capture in Booster Ring - Successfully transferring electrons from the LINAC to the booster ring, where they are further accelerated before being sent to the storage ring. | 3 weeks |
☐ | LINAC Frequency Variation Commissioning for Decay Mode – Conditioning the LINAC to operate across the full range of RF frequencies required to track the varying RF frequency of the storage ring, which shifts to compensate for changes in ring circumference during operations. | 2 weeks |
☐ | Beam Into the Storage Ring for Decay Mode - Injecting and maintaining beam in the storage ring. This phase will allow us to verify basic functionality of the storage ring. | 1 week |
☐ | CLS Planned Outage Fall 2025 – This outage has been shortened by two weeks from our original plan and is now set to run from August 25 to October 7, coinciding with a University of Saskatchewan planned power outage that will enable refurbishment of the facility’s 480V electrical supply. The remainder of the outage is needed to complete annual certifications of safety systems in several beamline and accelerator areas. | 44 days |
☐ | Verification and Post Outage Recovery - System-wide checks and calibrations following the planned outage to ensure all systems are functioning correctly before resuming beam delivery. | 1 week |
☐ | Low Quality Beam to Beamlines - Initial delivery of beam to beamlines with reduced stability and quality, used for identification and resolution of problems with the storage ring electron beam and beamlines. | 3 weeks |
☐ | Reliable Beam Delivered - Achievement of stable, high-quality beam delivery to beamlines. While we cannot guarantee top-up operations at this time, this critical milestone will enable us to check the full functionality of our beamlines and marks the return to normal research operations. | 1 week |
The latest news...

June 12, 2025: We are encouraged to share that a path towards resuming normal operations has been established. Full details of the milestone steps are included below. While there is still significant uncertainty around the exact timing of each stage, current projections suggest that low-quality, unreliable beam may be delivered to the storage ring during the summer months, though it will not be suitable for scientific use. Reliable beam is tentatively anticipated by late November 2025, pending continued success in commissioning and system validation. As the technical team works through this complex process, we expect to encounter and resolve minor technical challenges, supported by a strong and productive collaboration with our vendors. With the completion of each milestone, our confidence in predicting the date of our return to operations will increase; however, at this stage, there is not sufficient certainty to begin rescheduling any beamtime.
We recognize how disruptive this extended outage has been and are extremely sorry for the impact it has had on your research, your students, your collaborators, and your plans. Both the Board and executive leadership share your concerns and are committed to ensuring that the resources and institutional support necessary to complete this work are in place. The entire CLS team remains fully committed to restoring operations as safely and swiftly as possible. We are incredibly grateful for your patience, understanding, and continued support during this time. We look forward with real excitement to welcoming users back to the CLS later this year and supporting the important work about which we are all so passionate.
To help support users navigating funding challenges resulting from these delays, we intend to prepare an open letter outlining the broader LINAC-related disruption at CLS. Once we have greater clarity on the full duration and impact of the outage, this letter will be publicly posted on our website for users to reference or include in grant applications or related correspondence to help contextualize the interruption in research access that may have affected their work, independent of any project-specific factors. If you would benefit from this type of supporting documentation prior to its public release, please contact the CLS User Services Office for assistance.
We will continue to provide detailed updates as we move through each stage of the process, or in early July at the latest. In the meantime, we encourage you to visit our website and follow our social media channels for the latest information.
Bill Matiko Chief Executive Officer Canadian Light Source |
Ingrid Pickering Chief Science Officer Canadian Light Source |
Martha Crago Chair CLS Board of Directors |
Baljit Singh Vice-President Research University of Saskatchewan |



April 11, 2025: We have made meaningful progress in commissioning our new linear accelerator (linac). Our team of staff from CLS and RI Research Instruments GmbH (RI), our vendor, have been consulting with experts from other facilities, including an on-site visit from a MAX IV linac expert, to learn from their experience and approaches in conditioning a linac similar to ours. Following expert advice, we completed a bake-out of one linac section, which improved vacuum conditions and overall system performance. We have also modified our radiofrequency (RF) conditioning strategy to adopt a more gradual process. This slower approach is already yielding positive results.
Based on these encouraging developments, we now plan to bake out all three linac sections before continuing with our revised RF conditioning strategy, with the potential for some beam delivery to the storage ring as early as July. While this is an important step in restoring user operations, any storage ring beam at this stage would likely be unstable, which is not suitable for research use. Therefore, we remain unable to provide a definitive schedule for our return to normal operations and will provide a more concrete timeline as our technical work advances. We are enormously grateful for your continued patience and understanding as we work to restore operations.

March 27, 2025: The process of baking out accelerator section 3 began on March 19, 2025. This heating process will take about a week and should be complete soon. After that, all the diagnostic tools will be moved to section 3, and the next step - RF conditioning - should start on March 28, 2025. If the bakeout of section 3 provides improvement to the RF conditioning, we will do the same for the other two structures. otherwise we will focus on delivering user beam with current conditions.
Experts from MAX IV, Sweden’s national synchrotron, will visit CLS starting on March 31, 2025 for a week, to support our ongoing efforts. Max IV's new linac is very similar to CLS’s and their experience bringing their system online will be invaluable as we work towards stable user beam.
In parallel to the heating up of section 3, we resumed RF conditioning of section 1 on March 19, 2025. Section 1 is currently at around 26MW at 0.2 microseconds, and our goal is to reach 30MW at 4.5 microseconds. We have collected data from microphones and directional couplers at each end of sections 1 and 3 to find out where the issues are. This data, which we’re sharing with the LINAC vendor, Research Instruments (RI), and our colleagues from other facilities – including CERN, MAX IV, SLAC, and Elettra - shows that there might be arcing near the section input couplers.
We are grateful for everyone’s patience as we put all our efforts towards bringing beam back.

March 4, 2025: A joint message from CLS and RI: Last year the Canadian Light Source (CLS) contracted RI Research Instruments GmbH (RI) to design, build, install, and commission a new linear accelerator (LINAC). While installation of CLS’s new LINAC was completed successfully and on time in August 2024, problems encountered during commissioning have prevented the CLS from resuming regular operations. Staff from RI and the CLS are working around the clock – onsite and remotely – to determine the cause of the setback and to restore beam to CLS users as soon as possible.
Together, RI and CLS have been carrying out a multifaceted investigation of the problem, including a thorough inspection and qualification of all the LINAC RF components, as well as new RF diagnostics and RF pieces. The new RF components have either been loaned or purchased by RI, or fabricated by RI or CLS, and have been qualified onsite at the facility. Because of the time required to carry out this troubleshooting, CLS must regrettably cancel a large portion of scheduled user time in 2025.
The unexpected problems encountered in commissioning the RI LINAC – a product known for its robustness and successful operation in labs around the world – have prompted our two organizations to seek external expertise from other accelerator laboratories. We are soliciting input on the design, quality assurance processes, and the commissioning methodology. In anticipation of the potential need to replace accelerating structures and to minimize the schedule impact, RI is already manufacturing structures and procuring the copper needed if more structures are required.
Our two organizations are aligned in our shared goals to have CLS resume user operations as soon as possible and to provide the LINAC to original specification.
Bill Matiko
Chief Executive Officer
CLS
Michael Pekeler and Christian Piel
Managing Partners
RI Research Instruments GmbH
























June 6, 2024: With the old linac equipment removed from our basement, our health and safety staff needed to scan these pieces for radiation before they could be recycled or donated. They have now checked over 175 items! Next, we cleaned the linac hallways and started giving them a fresh coat of paint. Our staff also fully dismantled our modulator room. Klystrons, modulators, and other infrastructure were removed, making way for the mechanical and electrical service installation that is now ongoing. We have new modulators and klystrons waiting on our experimental floor. This equipment will provide the radiofrequency energy that is used to accelerate electrons through our linac before they produce synchrotron light for research.

May 30, 2024: The CLS has been dark for a short time, but there has already been a significant amount of progress thanks to our hard-working team. Once our operators turned off the machine, we soon started to dismantle the electron source and linear accelerator in our basement. Our staff have already removed the power supply tank, accelerating sections, and other assorted infrastructure. About 90% of the removed equipment will be recycled and the remaining 10% will be donated to universities or museums. The appearance of our basement has already changed dramatically. The linac hallways that are usually filled with specialized equipment are looking quite empty. While it may seem that this project has just begun, years of planning have led us to this point to help ensure the transition goes as quickly and smoothly as possible. Our team of engineers, technicians, physicists, and many others carefully prepared for when the key was turned for the final time and the six months of work that would follow. Installing a new linac will ensure the CLS provides high-quality, reliable synchrotron light for innovative research for years to come.

May 27, 2024: Starting today, the Canadian Light Source (CLS) at the University of Saskatchewan will begin work to replace its linear accelerator (linac) - the system that speeds up electrons to produce the ultrabright light researchers use to study materials at the molecular or cellular level. The new linac will replace aging infrastructure from the Saskatchewan Accelerator Laboratory that dates back to the 1960s and the early days of the CLS, and will enhance the facility’s efficiency and reliability. Over the next six months, staff will remove the old linac, its electron source and associated operating systems and refurbish the underground tunnel in which it is located. A new linac with a shorter and more modern design will then be installed, including accelerating devices, electromagnets, high-power radiofrequency transmitters, computer control system and ancillary systems, under the direction and supervision of the vendor, Research Instruments (Germany), who designed and built the system. Read more